EstatePass
Business & FinanceAdminmedium26% of exam part

A project requires the contractor to submit monthly payment applications. The contract value is $500,000, and 60% of the work is complete. If the contract includes 10% retention, what is the amount due to the contractor?

Correct Answer

B) $270,000

Work completed = $500,000 × 0.60 = $300,000. With 10% retention held: $300,000 - ($300,000 × 0.10) = $300,000 - $30,000 = $270,000. Retention is held until project completion.

Answer Options
A
$330,000
B
$270,000
C
$300,000
D
$450,000

Why This Is the Correct Answer

The correct answer is A) $270,000 because it properly calculates the payment due after retention. First, we determine the value of work completed (60% of $500,000 = $300,000). Then we subtract the 10% retention that the owner holds back ($300,000 × 10% = $30,000). The contractor receives $300,000 - $30,000 = $270,000. Retention is a standard practice where owners withhold a percentage of each payment until project completion to ensure contractor performance.

Why the Other Options Are Wrong

Option C: $300,000

This amount doesn't correspond to any logical calculation in the retention process and appears to add rather than subtract retention.

Option D: $450,000

This represents 90% of the total contract value rather than 90% of the completed work value, ignoring that only 60% of the work is actually complete.

Memory Technique

Remember 'CPR': Complete work value, then subtract Percentage Retention. Think 'Complete first, Retain second' - you can't retain what hasn't been completed yet.

Reference Hint

Florida Building Code Chapter 1, Section 105 - Permits and Construction Documents, or AIA Contract Documents regarding payment procedures and retention

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.