A project requires the contractor to submit monthly payment applications. The contract value is $500,000, and 60% of the work is complete. If the contract includes 10% retention, what is the amount due to the contractor?
Correct Answer
B) $270,000
Work completed = $500,000 × 0.60 = $300,000. With 10% retention held: $300,000 - ($300,000 × 0.10) = $300,000 - $30,000 = $270,000. Retention is held until project completion.
Why This Is the Correct Answer
The correct answer is A) $270,000 because it properly calculates the payment due after retention. First, we determine the value of work completed (60% of $500,000 = $300,000). Then we subtract the 10% retention that the owner holds back ($300,000 × 10% = $30,000). The contractor receives $300,000 - $30,000 = $270,000. Retention is a standard practice where owners withhold a percentage of each payment until project completion to ensure contractor performance.
Why the Other Options Are Wrong
Option C: $300,000
This amount doesn't correspond to any logical calculation in the retention process and appears to add rather than subtract retention.
Option D: $450,000
This represents 90% of the total contract value rather than 90% of the completed work value, ignoring that only 60% of the work is actually complete.
Memory Technique
Remember 'CPR': Complete work value, then subtract Percentage Retention. Think 'Complete first, Retain second' - you can't retain what hasn't been completed yet.
Reference Hint
Florida Building Code Chapter 1, Section 105 - Permits and Construction Documents, or AIA Contract Documents regarding payment procedures and retention
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
Which of the following is NOT typically considered a startup cost for a new contracting business?
Next Question
A construction company pays a subcontractor $45,000 annually and provides all tools and equipment. The subcontractor works exclusively for this company and follows their daily schedule. Based on IRS guidelines, this arrangement most likely indicates:
