A project milestone shows 'Building Envelope Complete' scheduled for Day 120. On Day 115, the roofing is 90% complete and exterior walls are 85% complete. What is the current status of this milestone?

Correct Answer

B) Milestone is behind schedule

With only 5 days remaining and roofing at 90% and walls at 85%, it's unlikely both will be 100% complete by Day 120. The milestone appears behind schedule based on current progress rates.

Answer Options
A
Milestone is on track to complete on time
B
Milestone is behind schedule
C
Milestone completion cannot be determined from given information
D
Milestone is complete

Why This Is the Correct Answer

With only 5 days remaining and roofing at 90% and walls at 85%, it's unlikely both will be 100% complete by Day 120. The milestone appears behind schedule based on current progress rates.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.