A project manager is tracking costs on a commercial building project. The budget allocates 35% for materials, 40% for labor, 15% for equipment, and 10% for overhead. If the total project budget is $3.5 million, what is the materials budget?

Correct Answer

B) $1,225,000

Materials budget = Total budget × Materials percentage = $3,500,000 × 35% = $1,225,000.

Answer Options
A
$525,000
B
$1,225,000
C
$1,400,000
D
$350,000

Why This Is the Correct Answer

Materials budget = Total budget × Materials percentage = $3,500,000 × 35% = $1,225,000.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.