EstatePass
Business & FinanceOperationseasy10% of exam part

A project manager discovers that steel delivery is delayed, but the affected activities have 6 days of total float. The delay is expected to be 4 days. What is the impact on the project completion date?

Correct Answer

C) No impact on project completion date

Since the activities have 6 days of total float and the delay is only 4 days, the delay can be absorbed within the available float without affecting the project completion date.

Answer Options
A
Project will be delayed by 4 days
B
Project will be delayed by 6 days
C
No impact on project completion date
D
Project will be delayed by 2 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. Since the steel delivery delay is only 4 days and the affected activities have 6 days of total float available, the entire delay can be absorbed within the existing float. This means there is still 2 days of float remaining (6 - 4 = 2) and no impact on the critical path or project completion date.

Why the Other Options Are Wrong

Option A: Project will be delayed by 4 days

This assumes the delay directly impacts the project completion date, but ignores the concept of float. When activities have total float available, delays up to that float amount do not affect project completion.

Option D: Project will be delayed by 2 days

This confuses the available float time with project delay. The 6 days represents the buffer time available, not the amount of delay that would occur.

Memory Technique

Float = Buffer. Think of float as a 'cushion' that absorbs delays. As long as the delay fits within the cushion, the project stays on schedule.

Reference Hint

Project Management chapter covering Critical Path Method (CPM), specifically sections on float calculations and schedule analysis

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.