A project has the following activities on the critical path: Foundation (5 days), Framing (12 days), Roofing (8 days), and Electrical rough-in (6 days). If the roofing activity is delayed by 3 days due to weather, what is the impact on the project completion date?

Correct Answer

C) Project is delayed by 3 days

Since roofing is on the critical path, any delay to this activity directly impacts the project completion date. A 3-day delay in roofing will delay the entire project by 3 days.

Answer Options
A
Project is delayed by 1 day
B
Project is delayed by 8 days
C
Project is delayed by 3 days
D
No impact, as roofing has float time available

Why This Is the Correct Answer

Since roofing is on the critical path, any delay to this activity directly impacts the project completion date. A 3-day delay in roofing will delay the entire project by 3 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.