A project has the following activities: A(4 days) → B(6 days) → D(3 days) and A(4 days) → C(8 days) → D(3 days). Activity D cannot start until both B and C are complete. What is the critical path duration?
Correct Answer
B) 15 days
Path 1: A(4) + B(6) + D(3) = 13 days. Path 2: A(4) + C(8) + D(3) = 15 days. The critical path is the longest path, which is 15 days through A-C-D.
Why This Is the Correct Answer
The critical path is the longest sequence of activities that determines the minimum project duration. In this network, there are two possible paths from start to finish: A-B-D (13 days) and A-C-D (15 days). Since Activity D cannot start until both B and C are complete, we must wait for the longer path (A-C-D) to finish before D can begin. Therefore, the critical path duration is 15 days.
Why the Other Options Are Wrong
Option A: 19 days
17 days is incorrect as it doesn't correspond to any valid path calculation in this network. The longest path A-C-D only totals 15 days (4+8+3), not 17 days.
Option C: 17 days
13 days represents only the duration of path A-B-D, but this ignores the constraint that Activity D cannot start until both B and C are complete. Since path A-C-D takes 15 days, D cannot actually start after only 13 days.
Memory Technique
Remember 'LONGEST = CRITICAL' - the critical path is always the longest duration path through your project network, as it controls when your project can finish.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections of contractor reference materials.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
A Florida contractor's SUTA rate is 2.7% on the first $7,000 of wages per employee. With 8 employees each earning over $7,000 annually, what is the total SUTA liability?
Next Question
During a performance evaluation, a supervisor documents that an employee 'needs improvement in punctuality and attention to detail.' What is the most important next step in the evaluation process?
