A project has incurred costs of $75,000 and is 40% complete based on cost-to-cost method. If the total contract value is $200,000, what amount should be recognized as earned revenue?
Correct Answer
A) $80,000
Using percentage of completion method: Earned revenue = Contract value × Percentage complete = $200,000 × 40% = $80,000. This matches the progress of work completed.
Why This Is the Correct Answer
The percentage of completion method calculates earned revenue by multiplying the total contract value by the percentage of work completed. Since the project is 40% complete and the contract value is $200,000, the earned revenue is $200,000 × 40% = $80,000. This method ensures revenue recognition matches the actual progress of work performed, which is a fundamental principle in construction accounting.
Why the Other Options Are Wrong
Option B: $125,000
This appears to be an incorrect calculation, possibly mixing up the remaining contract value or applying the percentage incorrectly. The calculation should be straightforward: total contract value times percentage complete.
Option D: $75,000
This amount ($125,000) doesn't correspond to any logical calculation using the given data. It's not 40% of the contract value, nor does it relate to the costs incurred in any standard accounting method.
Memory Technique
Remember 'Contract × Complete = Cash earned' - always use the total contract value times the completion percentage for earned revenue calculations.
Reference Hint
Look up 'Percentage of Completion Method' or 'Revenue Recognition' in construction accounting sections, typically found in business law or accounting chapters of contractor reference materials.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
A contractor purchased office furniture for $15,000 and computer equipment for $8,000. Using straight-line depreciation over 7 years for furniture and 5 years for computers, what is the total annual depreciation?
Next Question
Under FEMA requirements, what type of construction documentation must be maintained in flood-prone areas?
