EstatePass
Business & FinanceOperationsmedium10% of exam part

A project has activities with the following durations and dependencies: Activity A (5 days), Activity B (3 days, depends on A), Activity C (4 days, depends on A), Activity D (2 days, depends on B and C). What is the critical path duration?

Correct Answer

D) 11 days

The critical path is A→C→D (5+4+2=11 days) or A→B→D (5+3+2=10 days). Since C takes longer than B, the critical path duration is 11 days through A→C→D.

Answer Options
A
9 days
B
12 days
C
14 days
D
11 days

Why This Is the Correct Answer

The critical path is the longest sequence of dependent activities that determines the minimum project duration. To find it, we calculate all possible paths from start to finish and identify the one with the greatest total duration. Path A→C→D totals 11 days (5+4+2), while path A→B→D totals 10 days (5+3+2), making A→C→D the critical path at 11 days.

Why the Other Options Are Wrong

Option B: 12 days

14 days is incorrect because it appears to add all activity durations (5+3+4+2=14), but this ignores the network logic where activities B and C run in parallel after A, not sequentially.

Option C: 14 days

9 days is incorrect because it's less than both possible paths through the network. This might result from miscalculating one of the paths or forgetting to include all required activities in the sequence.

Memory Technique

Remember 'LONGEST = CRITICAL' - the critical path is always the longest duration path through your project network, not the shortest or most convenient route.

Reference Hint

Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.