A project has activities with the following durations: A(5 days), B(8 days), C(6 days), D(4 days). The network shows A→C→D and B→D as parallel paths. What is the critical path duration?
Correct Answer
D) 15 days
Path A→C→D = 5+6+4 = 15 days. Path B→D = 8+4 = 12 days. The critical path is the longest path, which is A→C→D at 15 days.
Why This Is the Correct Answer
The critical path is the longest sequence of activities that determines the minimum project duration. To find it, we calculate the total duration of each possible path through the network. Path A→C→D takes 5+6+4=15 days, while path B→D takes 8+4=12 days. Since 15 days is longer than 12 days, the critical path duration is 15 days.
Why the Other Options Are Wrong
Option A: 23 days
23 days would result from incorrectly adding all activity durations together (5+8+6+4=23), which ignores that activities B and A→C occur in parallel, not sequentially.
Option C: 17 days
12 days represents the duration of path B→D (8+4=12), which is the shorter path and therefore not the critical path.
Memory Technique
Remember 'LONGEST = CRITICAL' - the critical path is always the longest path through the network, just like the critical bottleneck determines overall project completion time.
Reference Hint
Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters - typically found in project management sections of contractor reference books.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
