EstatePass
Business & FinanceOperationseasy10% of exam part

A project has activities A (5 days), B (3 days), and C (7 days). Activity A must be completed before B starts, and B must be completed before C starts. What is the total project duration using CPM scheduling?

Correct Answer

A) 15 days

Since the activities are sequential (A→B→C), the total project duration is the sum of all activity durations: 5 + 3 + 7 = 15 days. This represents the critical path for this project.

Answer Options
A
15 days
B
12 days
C
7 days
D
10 days

Why This Is the Correct Answer

In CPM scheduling with sequential activities, the total project duration equals the sum of all activity durations along the critical path. Since Activity A must finish before B starts, and B must finish before C starts, there is no overlap or parallel work possible. The critical path is A→B→C, making the total duration 5 + 3 + 7 = 15 days. This represents the longest path through the project network and determines the minimum project completion time.

Why the Other Options Are Wrong

Option B: 12 days

12 days would be the sum of only Activities A and B (5 + 3 + 4 missing days), but this fails to include the full 7-day duration of Activity C that must follow.

Option D: 10 days

10 days is insufficient time to complete all three sequential activities, as it's 5 days short of the required 15 days needed for the complete A→B→C sequence.

Memory Technique

Remember 'Sequential = Sum' - when activities must be done one after another (sequential), the total time is the sum of all individual activity times.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections of contractor reference materials.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.