A project contract includes liquidated damages of $500 per day for delays. The project is 12 days behind schedule due to weather delays beyond the contractor's control. What is the contractor's liability?
Correct Answer
B) $0
Weather delays beyond the contractor's control typically qualify for time extensions, which excuse liquidated damages. Contractors are generally not liable for damages during excusable delays, provided proper notice and documentation are provided.
Why This Is the Correct Answer
Weather delays beyond the contractor's control are considered excusable delays that typically qualify for time extensions under most construction contracts. When an excusable delay occurs, the contractor is generally relieved from liquidated damages liability for that period, provided they give proper notice and maintain adequate documentation. The key principle is that contractors should not be penalized for delays caused by circumstances outside their reasonable control, such as severe weather conditions.
Why the Other Options Are Wrong
Option A: $1,500
$6,000 would be the calculation if liquidated damages applied (12 days Γ $500 = $6,000), but this ignores the excusable nature of weather delays
Option C: $6,000
$1,500 also suggests partial liability, but excusable delays like uncontrollable weather generally provide full relief from liquidated damages
Option D: $3,000
$3,000 suggests partial liability, but weather delays beyond contractor control typically provide complete relief from liquidated damages, not partial relief
Memory Technique
Think 'Weather = Waiver' - uncontrollable weather conditions typically waive liquidated damages liability
Reference Hint
Florida Building Code Chapter 1, Section 105 - Construction Documents and Permits, or contract law sections covering time extensions and excusable delays
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
