A materials supplier delivers $8,000 worth of lumber to a job site on January 10th and delivers the final load worth $2,000 on February 5th. When must the supplier file their lien claim by?
Correct Answer
A) May 6th
The 90-day lien filing period begins from the last delivery of materials, which was February 5th. Adding 90 days gives a deadline of May 6th.
Why This Is the Correct Answer
Georgia law requires a lien to be filed within 90 days of the last furnishing of materials. The last delivery was February 5th. Counting 90 days forward from February 5th: February has 28 days in a non-leap year, so 28 - 5 = 23 more days in February, then 31 days in March, then 31 days in April = 23 + 31 + 31 = 85 days through April 30th, leaving 5 more days into May = May 5th. However, since February 5th is day 0, day 90 lands on May 6th. The lien must be filed by May 6th.
Why the Other Options Are Wrong
Option B: March 11th
March 11th would be only about 34 days after the last delivery (February 5th + ~34 days). This corresponds to incorrectly counting 30 days from the first delivery date (January 10th), which is wrong on two counts: the clock starts from the last furnishing, and the window is 90 days, not 30.
Option C: April 5th
April 5th is exactly 59 days after February 5th β roughly 60 days, not 90. This answer results from using an incorrect 60-day window or confusing Georgia's deadline with another state's shorter period.
Option D: April 10th
April 10th is 90 days after January 10th β the date of the first delivery. This is the classic trap: using the first delivery date instead of the last delivery date. Georgia law clearly starts the 90-day clock from the last furnishing of labor or materials.
Memory Technique
Remember: 'Last in, last clock.' The 90-day lien clock starts on the last day you supplied anything to the project. Ignore earlier deliveries when calculating the deadline β only the most recent one matters. February 5th + 90 days = May 6th.
More Georgia Questions
A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?
A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?
Which situation would require a Georgia contractor to obtain workers' compensation insurance?
A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?
A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?
A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?
A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?
A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?
A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?
What is the threshold amount above which a contractor must be licensed in Georgia?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
