EstatePass
GeorgiaGA Supplementmedium100% of exam part

A materials supplier delivers $8,000 worth of lumber to a job site on January 10th and delivers the final load worth $2,000 on February 5th. When must the supplier file their lien claim by?

Correct Answer

A) May 6th

The 90-day lien filing period begins from the last delivery of materials, which was February 5th. Adding 90 days gives a deadline of May 6th.

Answer Options
A
May 6th
B
March 11th
C
April 5th
D
April 10th

Why This Is the Correct Answer

Georgia law requires a lien to be filed within 90 days of the last furnishing of materials. The last delivery was February 5th. Counting 90 days forward from February 5th: February has 28 days in a non-leap year, so 28 - 5 = 23 more days in February, then 31 days in March, then 31 days in April = 23 + 31 + 31 = 85 days through April 30th, leaving 5 more days into May = May 5th. However, since February 5th is day 0, day 90 lands on May 6th. The lien must be filed by May 6th.

Why the Other Options Are Wrong

Option B: March 11th

March 11th would be only about 34 days after the last delivery (February 5th + ~34 days). This corresponds to incorrectly counting 30 days from the first delivery date (January 10th), which is wrong on two counts: the clock starts from the last furnishing, and the window is 90 days, not 30.

Option C: April 5th

April 5th is exactly 59 days after February 5th β€” roughly 60 days, not 90. This answer results from using an incorrect 60-day window or confusing Georgia's deadline with another state's shorter period.

Option D: April 10th

April 10th is 90 days after January 10th β€” the date of the first delivery. This is the classic trap: using the first delivery date instead of the last delivery date. Georgia law clearly starts the 90-day clock from the last furnishing of labor or materials.

Memory Technique

Remember: 'Last in, last clock.' The 90-day lien clock starts on the last day you supplied anything to the project. Ignore earlier deliveries when calculating the deadline β€” only the most recent one matters. February 5th + 90 days = May 6th.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.