A material supplier delivers $12,000 worth of materials to a job site on April 10th. The last delivery is made May 5th. Under Alabama lien law, what is the deadline to file a lien claim?

Correct Answer

C) November 5th

Material suppliers must file lien claims within 6 months of their last delivery. Six months from May 5th is November 5th.

Answer Options
A
December 5th
B
October 10th
C
November 5th
D
January 5th

Why This Is the Correct Answer

Material suppliers must file lien claims within 6 months of their last delivery. Six months from May 5th is November 5th.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.