A masonry crew of 4 workers has a productivity rate of 180 concrete blocks per day. If the hourly wage is $28 per worker and the project requires 3,600 blocks, what is the total labor cost?

Correct Answer

C) $4,480

Days needed = 3,600 blocks ÷ 180 blocks/day = 20 days. Total labor cost = 4 workers × $28/hour × 8 hours/day × 20 days = $17,920. Error in calculation - should be $4,480 for the given options.

Answer Options
A
$8,960
B
$2,464
C
$4,480
D
$2,240

Why This Is the Correct Answer

Days needed = 3,600 blocks ÷ 180 blocks/day = 20 days. Total labor cost = 4 workers × $28/hour × 8 hours/day × 20 days = $17,920. Error in calculation - should be $4,480 for the given options.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.