A job has a contract value of $500,000 with costs to date of $300,000 and estimated costs to complete of $150,000. Using the percentage-of-completion method, what percentage of the job is complete?
Correct Answer
C) 67%
Percentage complete = Costs to date ÷ Total estimated costs. Total estimated costs = $300,000 + $150,000 = $450,000. $300,000 ÷ $450,000 = 66.7% or approximately 67%.
Why This Is the Correct Answer
The percentage-of-completion method calculates project completion based on costs incurred versus total estimated costs, not contract value. The formula is: Costs to date ÷ Total estimated costs. Total estimated costs equals costs to date ($300,000) plus estimated costs to complete ($150,000) = $450,000. Therefore, $300,000 ÷ $450,000 = 0.667 or 67%.
Why the Other Options Are Wrong
Option B: 80%
75% appears to use an incorrect total cost figure, possibly excluding some costs or using the wrong denominator in the calculation.
Option D: 60%
60% incorrectly uses the contract value in the calculation ($300,000 ÷ $500,000 = 60%), but percentage-of-completion is based on costs, not contract value.
Memory Technique
Remember 'CTC' - Costs To Complete: Add costs to date + costs to complete for your denominator, then divide costs to date by that total.
Reference Hint
Look up 'Percentage-of-Completion Method' or 'Project Accounting' in construction management or accounting sections of your reference materials.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
