A general contractor wishes to make a change order that increases the original home improvement contract price by $800. Under B&P Code 7159, what documentation is required?

Correct Answer

A) Written change order signed by the customer

B&P Code 7159(d) requires all change orders that alter the contract terms to be in writing and signed by the customer, regardless of the dollar amount. This protects both parties and ensures clear documentation of agreed-upon modifications.

Answer Options
A
Written change order signed by the customer
B
Email confirmation from the customer
C
Written change order with 24-hour waiting period
D
Verbal agreement only is sufficient for changes under $1,000

Why This Is the Correct Answer

B&P Code 7159(d) requires all change orders that alter the contract terms to be in writing and signed by the customer, regardless of the dollar amount. This protects both parties and ensures clear documentation of agreed-upon modifications.

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.