EstatePass
law-businessMechanics Lien LawEASY

A general contractor must record a mechanics lien claim within how many days after completion of a work of improvement under California Civil Code Section 8412?

Correct Answer

B) 90 days

California Civil Code Section 8412 requires a mechanics lien to be recorded within 90 days after completion of the work of improvement. For direct contractors, completion is determined by actual completion, cessation of labor, or acceptance by the owner. Missing this deadline results in loss of lien rights.

Answer Options
A
120 days
B
90 days
C
60 days
D
75 days

Why This Is the Correct Answer

California Civil Code §8412 gives a direct contractor 90 days from completion of the work of improvement to record a mechanics lien. 'Completion' is defined broadly — it can be actual completion, cessation of labor for a continuous 60-day period, or acceptance by the owner. Failing to record within 90 days permanently extinguishes the lien right.

Why the Other Options Are Wrong

Option A: 120 days

120 days is not the deadline for a direct contractor under §8412. This number may be confused with other California notice periods or with deadlines for subcontractors under different sections. The direct contractor deadline is 90 days.

Option C: 60 days

60 days is the deadline for subcontractors and material suppliers under §8414, not for direct contractors. This is the most common wrong answer because candidates confuse the two deadlines.

Option D: 75 days

75 days is not a statutory period under California lien law. It does not correspond to any deadline in the Civil Code's mechanics lien framework.

Memory Technique

Direct Contractor = 90 days. Sub/Supplier = 60 days. Remember: the GC has the biggest role and gets the most time — '90 for the boss, 60 for the subs.' Or think: 9-0 = GC goes first with 9 (multiplied by 10).

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing