A general contractor is managing material procurement for a project and discovers that steel delivery will be delayed by 2 weeks. The steel installation is on the critical path. What is the most appropriate immediate action?
Correct Answer
D) Expedite the steel delivery by finding alternative suppliers or paying premium shipping
Since the steel installation is on the critical path, any delay will directly impact project completion. Expediting through alternative suppliers or premium shipping is the most appropriate immediate response to minimize schedule impact.
Why This Is the Correct Answer
Option B is correct because critical path activities directly impact project completion dates, making any delay in steel delivery a project-threatening issue. As a general contractor, the immediate priority is to minimize schedule impact through proactive measures like finding alternative suppliers or expediting delivery. This approach demonstrates proper project management by taking decisive action to protect the overall project timeline. The additional cost of expediting is typically justified when compared to the potential penalties and costs associated with project delays.
Why the Other Options Are Wrong
Option A: Wait for the original steel order and accept the project delay
Option C is wrong because switching structural materials without proper engineering approval violates building codes, creates safety hazards, and exposes the contractor to significant liability for structural failures or code violations.
Option C: Switch to a different structural material without engineering approval
Option D is wrong because critical path delays cannot be recovered through acceleration of non-critical activities, and hoping to make up time without addressing the root cause is unrealistic and unprofessional project management.
Memory Technique
Think 'Critical = Crisis' - critical path delays require immediate crisis management, not passive acceptance or unauthorized changes
Reference Hint
Project Management chapter in contractor reference manual, specifically sections on Critical Path Method (CPM) and schedule management
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
Under the Americans with Disabilities Act, what constitutes an 'undue hardship' that would excuse an employer from providing reasonable accommodation?
Next Question
A contractor hires 15 framers for a 6-month project at $28 per hour. Each framer works 40 hours per week. What is the total labor cost for this crew over the project duration?
