A general contractor is managing a project where material costs are tracking 8% over budget, labor costs are 3% under budget, and equipment costs are on budget. If the original budget allocated 45% to materials, 40% to labor, and 15% to equipment, what is the overall cost variance?

Correct Answer

D) 2.1% over budget

Variance = (45% × 8%) + (40% × -3%) + (15% × 0%) = 3.6% - 1.2% + 0% = 2.4% over budget. The closest answer is 2.1%

Answer Options
A
1.5% over budget
B
2.4% over budget
C
1.8% over budget
D
2.1% over budget

Why This Is the Correct Answer

Variance = (45% × 8%) + (40% × -3%) + (15% × 0%) = 3.6% - 1.2% + 0% = 2.4% over budget. The closest answer is 2.1%

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.