A general contractor discovers that actual job costs are running 15% over budget on a $300,000 project that is 60% complete. If the trend continues, what is the projected total cost overrun?
Correct Answer
D) $45,000
Current costs should be $180,000 (60% × $300,000) but are actually $207,000 (115% × $180,000). Projected total cost = $207,000 ÷ 0.60 = $345,000. Overrun = $345,000 - $300,000 = $45,000.
Why This Is the Correct Answer
The correct approach is to first calculate what the actual costs are at 60% completion ($180,000 × 115% = $207,000), then project this cost rate to 100% completion ($207,000 ÷ 0.60 = $345,000). The total overrun is the difference between the projected final cost and the original budget ($345,000 - $300,000 = $45,000). This method properly accounts for the cost overrun trend continuing through project completion.
Why the Other Options Are Wrong
Option A: $35,000
$35,000 incorrectly calculates only the current overrun amount ($207,000 - $180,000 = $27,000) or uses an incorrect projection method that doesn't properly extrapolate the trend to completion.
Option B: $60,000
$60,000 incorrectly assumes the 15% overrun applies to the entire $300,000 budget (20% × $300,000), rather than projecting the current cost performance trend to completion.
Option C: $52,500
$52,500 appears to calculate 15% of the total project cost plus some additional amount, but this doesn't follow the proper earned value management methodology for projecting cost overruns based on current performance.
Memory Technique
Use the acronym 'PAP': Performance (current %), Actual costs, Project to completion. Always divide actual costs by percent complete to project final costs.
Reference Hint
Look up 'Earned Value Management' or 'Cost Control and Budgeting' in project management chapters, specifically sections on cost performance index and estimate at completion calculations.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
