A cut and fill operation requires moving 5,000 cubic yards of soil. The soil has a swell factor of 25% when excavated and a shrinkage factor of 8% when compacted. How many cubic yards of compacted fill will result?

Correct Answer

D) 4,600 cubic yards

Compacted volume = original volume × (1 - shrinkage factor) = 5,000 × (1 - 0.08) = 5,000 × 0.92 = 4,600 cubic yards.

Answer Options
A
5,000 cubic yards
B
5,250 cubic yards
C
4,750 cubic yards
D
4,600 cubic yards

Why This Is the Correct Answer

Compacted volume = original volume × (1 - shrinkage factor) = 5,000 × (1 - 0.08) = 5,000 × 0.92 = 4,600 cubic yards.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.