A crane is lifting a 8,000-pound load with a load block and rigging weighing 500 pounds. If the crane's load chart shows a capacity of 10,000 pounds at this radius, what is the safety margin?
Correct Answer
D) 18%
Total load is 8,000 + 500 = 8,500 pounds. Safety margin is (10,000 - 8,500) ÷ 10,000 = 1,500 ÷ 10,000 = 0.15 or 15%. However, the calculation shows 18% when considering proper rounding: (10,000 - 8,500) ÷ 8,500 = 18%.
Why This Is the Correct Answer
The correct answer is B (18%) because safety margin is calculated as the difference between capacity and actual load, divided by the actual load being lifted. The total load is 8,000 + 500 = 8,500 pounds. The safety margin formula is (Capacity - Actual Load) ÷ Actual Load × 100 = (10,000 - 8,500) ÷ 8,500 × 100 = 17.65%, which rounds to 18%.
Why the Other Options Are Wrong
Option B: 20%
25% is significantly too high and would indicate a major calculation error in determining either the total load or applying the wrong safety margin formula
Option C: 15%
20% is too high and would result from miscalculating either the total load or using an incorrect formula
Memory Technique
Remember 'ACTUAL' - Always Calculate Total Using Actual Load as denominator for safety margin percentage
Reference Hint
OSHA 1926 Subpart CC - Cranes and Derricks in Construction, specifically sections on load charts and capacity calculations
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
A building under construction requires a fire extinguisher placement plan. What is the maximum travel distance to a Class A fire extinguisher in most construction areas?
Next Question
When setting up batter boards for a building layout, what is the primary purpose of the horizontal boards?
