EstatePass
Business & FinanceAccountinghard32% of exam part

A contractor's project has actual costs of $85,000 against a budget of $90,000 and is 75% complete. What is the projected final cost using the cost-to-complete method?

Correct Answer

A) $113,333

If 75% complete with $85,000 spent, the projected final cost is $85,000 ÷ 0.75 = $113,333. This indicates a potential cost overrun.

Answer Options
A
$113,333
B
$90,000
C
$106,667
D
$95,000

Why This Is the Correct Answer

The cost-to-complete method projects final cost by dividing actual costs spent by the percentage of work completed. With $85,000 spent at 75% completion, the calculation is $85,000 ÷ 0.75 = $113,333. This method assumes the remaining work will continue at the same cost efficiency rate as the work completed so far. The result shows a significant cost overrun from the original $90,000 budget.

Why the Other Options Are Wrong

Option B: $90,000

This amount is too low and doesn't reflect the actual spending rate. It appears to be an arbitrary adjustment to the original budget rather than a calculation based on actual performance.

Option D: $95,000

This is the original budget amount, not the projected final cost based on current spending patterns. Using the original budget ignores the actual cost performance data.

Memory Technique

Think 'Spent over Done' - divide what you've Spent by what percentage is Done to get your projected total cost

Reference Hint

Project Management chapter, specifically sections on cost control, earned value management, and project cost forecasting methods

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.