A contractor receives three material quotes: $12,500, $11,800, and $13,200. The middle quote vendor requests a 5% deposit with order. What is the total initial cash outlay for this material purchase?

Correct Answer

C) $590

The middle quote of $11,800 requires a 5% deposit. Deposit amount = $11,800 × 5% = $590. This represents the initial cash outlay required to place the order.

Answer Options
A
$625
B
$660
C
$590
D
$11,800

Why This Is the Correct Answer

The question asks for the initial cash outlay for the material purchase, which means the deposit required upfront. The contractor would logically choose the middle quote of $11,800 as it's the most reasonable option between the three quotes. The 5% deposit on this amount equals $11,800 × 0.05 = $590, which represents the immediate cash requirement to secure the materials.

Why the Other Options Are Wrong

Option A: $625

This would be 5% of $13,200 ($660), but the contractor should choose the middle quote of $11,800, not the highest quote of $13,200.

Option B: $660

This represents the full amount of the middle quote, not the 5% deposit required. The initial cash outlay is only the deposit, not the entire purchase price.

Option D: $11,800

This would be 5% of $12,500 ($625), but the contractor should choose the middle quote of $11,800, not the highest quote of $12,500.

Memory Technique

Remember 'MID-DEP': Choose the MIDdle quote, calculate the DEPosit percentage. Initial cash outlay = deposit only, not full amount.

Reference Hint

Florida Building Construction Standards and Practices - Chapter on Project Cost Estimation and Material Procurement

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.