A contractor performs $50,000 worth of work but is only paid $35,000. If the contractor files a mechanics' lien for the unpaid balance, what amount can be claimed?
Correct Answer
B) $15,000
The unpaid balance is $50,000 - $35,000 = $15,000, which is the maximum amount that can be claimed in the mechanics' lien.
Why This Is the Correct Answer
The mechanics' lien can only be filed for the actual unpaid balance owed. $50,000 (total work) minus $35,000 (amount paid) = $15,000 unpaid. Georgia law limits the lien claim to the amount legitimately owed, not a punitive or inflated figure.
Why the Other Options Are Wrong
Option A: $20,000
$20,000 is incorrect. There is no basis for this figure β it does not result from any standard calculation using the numbers given ($50,000 - $35,000 = $15,000, not $20,000). A lien cannot exceed the actual unpaid amount.
Option C: $25,000
$25,000 is incorrect. This figure represents half the total contract value, not the unpaid balance. Liens are limited strictly to the amount of unpaid compensation, not a portion of the contract total.
Option D: $10,000
$10,000 is incorrect. This is less than the actual unpaid balance and has no basis in the given facts. Claimants are entitled to file for the full unpaid amount, and understating the lien would leave the contractor under-compensated.
Memory Technique
Think of a mechanics' lien like a receipt for what you haven't been paid yet. The lien = What You Did ($50,000) minus What You Got ($35,000) = What You're Owed ($15,000). No more, no less.
More Georgia Questions
A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?
A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?
Which situation would require a Georgia contractor to obtain workers' compensation insurance?
A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?
A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?
A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?
A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?
A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?
A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?
What is the threshold amount above which a contractor must be licensed in Georgia?