A contractor needs to remove concrete forms from a beam. The concrete was placed 5 days ago and has reached 70% of design strength. What is the appropriate action?
Correct Answer
B) Remove sides but leave bottom support
ACI standards allow removal of beam sides when concrete reaches sufficient strength (typically 70%), but bottom forms and supports must remain until the concrete reaches adequate strength to carry its own weight plus construction loads, usually 7-14 days.
Why This Is the Correct Answer
Option C correctly follows ACI standards for form removal timing. At 70% design strength (typically achieved in 3-7 days), concrete has sufficient strength to resist lateral pressure, allowing safe removal of side forms. However, the beam still needs bottom support to carry its own weight plus any construction loads until it reaches higher strength levels, typically requiring 7-14 days total.
Why the Other Options Are Wrong
Option A: Remove forms immediately
Removing all forms immediately would be unsafe because while the concrete has reached 70% strength for lateral support, it still needs bottom support to carry structural loads and prevent deflection or cracking.
Option C: Wait for full 28-day cure
Waiting until 7 days minimum is unnecessarily conservative for side form removal, as 70% strength is already adequate for removing sides, and this approach doesn't address the different requirements for side versus bottom support.
Memory Technique
Think 'SIDES FIRST' - sides come off when strong enough to hold shape, bottoms stay until strong enough to hold weight
Reference Hint
ACI 318 Building Code Requirements for Structural Concrete, Chapter 6 - Formwork and Shoring, or Florida Building Code Chapter 19
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A crane with a 150-foot boom is lifting materials near power lines. The power lines are rated at 50kV. What is the minimum clearance distance required between the crane and the energized power lines?
Next Question
What is the maximum allowable voltage for hand-held electric tools in wet conditions without GFCI protection?
