EstatePass
NASCLAContractsmedium15% of exam part

A contractor is working under a Cost-Plus-Fixed-Fee contract with a $2,500,000 estimated cost and a $200,000 fixed fee. If actual costs are $2,750,000, what is the contractor's total compensation?

Correct Answer

D) $2,950,000

In a Cost-Plus-Fixed-Fee contract, the contractor receives reimbursement for all allowable costs plus the fixed fee regardless of actual costs. Total compensation = $2,750,000 (actual costs) + $200,000 (fixed fee) = $2,950,000.

Answer Options
A
$2,500,000
B
$2,750,000
C
$2,700,000
D
$2,950,000

Why This Is the Correct Answer

$2,950,000 is correct. In a Cost-Plus-Fixed-Fee (CPFF) contract, the contractor is reimbursed for all allowable actual costs plus a pre-negotiated fixed fee that does not change regardless of actual costs. Total = $2,750,000 (actual costs) + $200,000 (fixed fee) = $2,950,000.

Why the Other Options Are Wrong

Option A: $2,500,000

$2,500,000 is incorrect β€” this is the original estimated cost only, with no fee included. Under a CPFF contract, the contractor receives reimbursement for actual costs, not estimated costs, plus the fixed fee.

Option B: $2,750,000

$2,750,000 is incorrect β€” this is the actual cost only, without adding the fixed fee. The contractor is always entitled to the fixed fee in addition to cost reimbursement, regardless of whether costs exceeded the estimate.

Option C: $2,700,000

$2,700,000 is incorrect β€” this appears to be the estimated cost plus the fixed fee ($2,500,000 + $200,000), ignoring the fact that actual costs ($2,750,000) exceeded the estimate. The contractor is reimbursed for actual costs, not estimated costs.

Memory Technique

CPFF = Actual Costs + Fixed Fee. The fee is 'fixed' β€” it stays at $200,000 no matter what. The cost portion uses ACTUAL, not estimated. Actual ($2.75M) + Fixed ($0.2M) = $2.95M.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.