A contractor is working under a Cost-Plus-Fixed-Fee contract with a $2,500,000 estimated cost and a $200,000 fixed fee. If actual costs are $2,750,000, what is the contractor's total compensation?
Correct Answer
D) $2,950,000
In a Cost-Plus-Fixed-Fee contract, the contractor receives reimbursement for all allowable costs plus the fixed fee regardless of actual costs. Total compensation = $2,750,000 (actual costs) + $200,000 (fixed fee) = $2,950,000.
Why This Is the Correct Answer
$2,950,000 is correct. In a Cost-Plus-Fixed-Fee (CPFF) contract, the contractor is reimbursed for all allowable actual costs plus a pre-negotiated fixed fee that does not change regardless of actual costs. Total = $2,750,000 (actual costs) + $200,000 (fixed fee) = $2,950,000.
Why the Other Options Are Wrong
Option A: $2,500,000
$2,500,000 is incorrect β this is the original estimated cost only, with no fee included. Under a CPFF contract, the contractor receives reimbursement for actual costs, not estimated costs, plus the fixed fee.
Option B: $2,750,000
$2,750,000 is incorrect β this is the actual cost only, without adding the fixed fee. The contractor is always entitled to the fixed fee in addition to cost reimbursement, regardless of whether costs exceeded the estimate.
Option C: $2,700,000
$2,700,000 is incorrect β this appears to be the estimated cost plus the fixed fee ($2,500,000 + $200,000), ignoring the fact that actual costs ($2,750,000) exceeded the estimate. The contractor is reimbursed for actual costs, not estimated costs.
Memory Technique
CPFF = Actual Costs + Fixed Fee. The fee is 'fixed' β it stays at $200,000 no matter what. The cost portion uses ACTUAL, not estimated. Actual ($2.75M) + Fixed ($0.2M) = $2.95M.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass