EstatePass
Project MgmtConstructionhard63% of exam part

A contractor is installing ceramic tile over a concrete slab. The slab has a moisture emission rate of 4.5 pounds per 1,000 square feet per 24 hours. What action should be taken?

Correct Answer

B) Apply a moisture barrier before tile installation

Moisture emission rates above 3 pounds per 1,000 square feet per 24 hours typically require a moisture barrier to prevent tile adhesive failure and potential mold issues.

Answer Options
A
Wait for the slab to cure longer before installation
B
Apply a moisture barrier before tile installation
C
Proceed with installation using standard methods
D
Use a different flooring material

Why This Is the Correct Answer

CORRECT_ANSWER - When moisture emission rates exceed 3 pounds per 1,000 square feet per 24 hours, a moisture barrier is required before tile installation. The measured rate of 4.5 pounds exceeds this threshold by 1.5 pounds, indicating significant moisture that could cause adhesive failure, tile debonding, and create conditions for mold growth. Installing a moisture barrier will prevent moisture from migrating through the concrete and compromising the tile installation.

Why the Other Options Are Wrong

Option C: Proceed with installation using standard methods

Proceeding with standard installation methods would be inappropriate because the moisture emission rate of 4.5 pounds exceeds the 3-pound threshold. This would likely result in tile adhesive failure, loose tiles, and potential mold issues due to trapped moisture.

Option D: Use a different flooring material

Changing to a different flooring material is unnecessarily drastic and costly when the issue can be properly addressed with a moisture barrier. Ceramic tile can still be successfully installed over concrete with elevated moisture levels when proper moisture mitigation measures are taken.

Memory Technique

Think '3 and FREE' - 3 pounds or less means you're free to install without barriers, above 3 pounds means you need protection

Reference Hint

Florida Building Code, Chapter 9 - Interior Finishes, or TCNA (Tile Council of North America) Handbook for ceramic tile installation over concrete

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.