A contractor is installing ceramic tile over a concrete slab. The slab has a moisture emission rate of 4.5 pounds per 1,000 square feet per 24 hours. What action should be taken?
Correct Answer
B) Apply a moisture barrier before tile installation
Moisture emission rates above 3 pounds per 1,000 square feet per 24 hours typically require a moisture barrier to prevent tile adhesive failure and potential mold issues.
Why This Is the Correct Answer
CORRECT_ANSWER - When moisture emission rates exceed 3 pounds per 1,000 square feet per 24 hours, a moisture barrier is required before tile installation. The measured rate of 4.5 pounds exceeds this threshold by 1.5 pounds, indicating significant moisture that could cause adhesive failure, tile debonding, and create conditions for mold growth. Installing a moisture barrier will prevent moisture from migrating through the concrete and compromising the tile installation.
Why the Other Options Are Wrong
Option C: Proceed with installation using standard methods
Proceeding with standard installation methods would be inappropriate because the moisture emission rate of 4.5 pounds exceeds the 3-pound threshold. This would likely result in tile adhesive failure, loose tiles, and potential mold issues due to trapped moisture.
Option D: Use a different flooring material
Changing to a different flooring material is unnecessarily drastic and costly when the issue can be properly addressed with a moisture barrier. Ceramic tile can still be successfully installed over concrete with elevated moisture levels when proper moisture mitigation measures are taken.
Memory Technique
Think '3 and FREE' - 3 pounds or less means you're free to install without barriers, above 3 pounds means you need protection
Reference Hint
Florida Building Code, Chapter 9 - Interior Finishes, or TCNA (Tile Council of North America) Handbook for ceramic tile installation over concrete
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A worker discovers an underground utility vault that needs to be entered for inspection. Before entry, what is the FIRST step that must be taken according to OSHA confined space procedures?
Next Question
When reading a section drawing, the cutting plane line with arrows indicates what information?
