A contractor is injured on a job site and files a workers compensation claim. The claim is valued at $85,000. If the experience modification factor increases from 1.0 to 1.25, what is the additional annual premium cost on a base premium of $12,000?
Correct Answer
C) $3,000
New premium = $12,000 × 1.25 = $15,000. Additional cost = $15,000 - $12,000 = $3,000
Why This Is the Correct Answer
Option C is correct. The new premium is calculated as: $12,000 (base) × 1.25 (new mod) = $15,000. The additional cost above the original premium of $12,000 × 1.0 = $12,000 is $15,000 − $12,000 = $3,000. The $85,000 claim value is a distractor — it does not factor into this calculation.
Why the Other Options Are Wrong
Option A: $3,600
Option A ($3,600) is incorrect. This would result from applying a 30% increase rather than the 25% increase from 1.0 to 1.25. ($12,000 × 0.30 = $3,600.)
Option B: $2,400
Option B ($2,400) is incorrect. This would result from applying a 20% increase. ($12,000 × 0.20 = $2,400.) The candidate may have confused the modifier change (0.25 above baseline) with a smaller percentage.
Option D: $4,200
Option D ($4,200) is incorrect. This would result from applying a 35% increase. ($12,000 × 0.35 = $4,200.) This may arise from adding the decimal modifier (0.25) to an incorrect baseline percentage.
Memory Technique
Experience mod math = Base × New Mod − Base × Old Mod = Base × (New − Old). Here: $12,000 × (1.25 − 1.0) = $12,000 × 0.25 = $3,000. Simply multiply the base premium by the mod change.
More Georgia Questions
A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?
A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?
Which situation would require a Georgia contractor to obtain workers' compensation insurance?
A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?
A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?
A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?
A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?
A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?
A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?
What is the threshold amount above which a contractor must be licensed in Georgia?