EstatePass
GeorgiaGA Supplementmedium100% of exam part

A contractor is building a single-family home in Georgia. The foundation inspection fails due to improper rebar placement. According to Georgia building codes, what is the next required step?

Correct Answer

D) Correct the deficiency and request re-inspection

When an inspection fails in Georgia, the contractor must correct all noted deficiencies and request a re-inspection before proceeding to the next phase of construction.

Answer Options
A
Hire a structural engineer to approve the work
B
File an appeal with the building department
C
Proceed with construction and address at final inspection
D
Correct the deficiency and request re-inspection

Why This Is the Correct Answer

When an inspection fails in Georgia, the proper procedure is to correct the deficiencies identified by the inspector and then request a re-inspection. Construction cannot proceed to the next phase until the failed inspection is passed. This is a fundamental building code compliance requirement.

Why the Other Options Are Wrong

Option A: Hire a structural engineer to approve the work

While a structural engineer may eventually be involved in complex situations, hiring one is not the mandatory next step following a failed inspection. The inspector has already identified the deficiency; the contractor must fix it and get re-inspected by the building department.

Option B: File an appeal with the building department

Filing an appeal is only appropriate when a contractor disputes the inspector's finding. The question states the rebar placement was actually improper β€” there is nothing to appeal. Appealing a legitimate failure would only delay the project.

Option C: Proceed with construction and address at final inspection

Proceeding with construction after a failed inspection is a serious code violation. In Georgia, it is illegal to continue to the next phase of construction before a failed inspection is corrected and re-inspected. Concrete poured over improperly placed rebar would require demolition.

Memory Technique

Failed inspection = STOP, FIX, CALL BACK. Stop work on that phase, fix the deficiency, then call back the inspector for re-inspection. No shortcuts, no skipping ahead.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.