A contractor is building a 2,500 square foot office building. The project disturbs 1.5 acres of land. What NPDES permit requirement applies?

Correct Answer

C) Notice of Intent (NOI) for stormwater permit required

NPDES requires a Notice of Intent (NOI) for stormwater permits when construction activities disturb one acre or more of land. Since this project disturbs 1.5 acres, an NOI is required to comply with federal stormwater regulations.

Answer Options
A
Individual permit required
B
No permit required
C
Notice of Intent (NOI) for stormwater permit required
D
Only local erosion control permit required

Why This Is the Correct Answer

The National Pollutant Discharge Elimination System (NPDES) requires a Notice of Intent (NOI) for stormwater permits when construction activities disturb one acre or more of land. This project disturbs 1.5 acres, which exceeds the one-acre threshold. The NOI is required under the Construction General Permit (CGP) to prevent stormwater pollution during construction activities. This is a federal requirement that applies regardless of building size or type.

Why the Other Options Are Wrong

Option A: Individual permit required

Option D is incorrect because while local erosion control permits may also be required, they do not satisfy federal NPDES requirements. The project must comply with both federal stormwater regulations (NPDES NOI) and any applicable local requirements.

Option D: Only local erosion control permit required

Option A is incorrect because the project disturbs 1.5 acres, which exceeds the one-acre threshold that triggers NPDES permit requirements. Any construction activity disturbing one acre or more requires stormwater permitting.

Memory Technique

Think 'ONE and DONE' - One acre triggers the requirement, and NOI gets it done for standard construction projects.

Reference Hint

Environmental regulations chapter or EPA Construction General Permit section in your reference materials

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.