EstatePass
Business & FinanceAdminhard26% of exam part

A contractor is bidding on a project with an estimated material cost of $150,000. If the historical material cost escalation rate is 3% annually and the project will start in 6 months, what should be the adjusted material cost estimate?

Correct Answer

D) $152,250

6 months = 0.5 years. Escalated cost = $150,000 × (1 + 0.03 × 0.5) = $150,000 × 1.015 = $152,250. The escalation should be prorated for the 6-month delay.

Answer Options
A
$150,000
B
$151,500
C
$154,500
D
$152,250

Why This Is the Correct Answer

The correct answer properly applies the time-proportional escalation formula for a 6-month delay. Since the project starts in 6 months (0.5 years), the 3% annual escalation rate must be prorated to 1.5% (3% × 0.5). The calculation $150,000 × (1 + 0.03 × 0.5) = $150,000 × 1.015 = $152,250 accurately reflects the expected material cost increase over the 6-month period. This method ensures the contractor accounts for inflation while not over-estimating costs for the actual time delay.

Why the Other Options Are Wrong

Option A: $150,000

This answer ($154,500) incorrectly applies the full 3% annual escalation rate without prorating for time: $150,000 × 1.03 = $154,500. This error assumes a full year of escalation when only 6 months will pass, resulting in an overestimate that could make the bid uncompetitive.

Option B: $151,500

This answer ignores escalation entirely, using the original $150,000 estimate. This approach fails to account for the 6-month delay and the 3% annual escalation rate, which would result in significant cost underestimation and potential financial losses for the contractor.

Memory Technique

Remember 'TIME MATTERS' - always prorate annual rates by the actual time fraction. Think: 6 months = half year = half the annual rate applied (3% ÷ 2 = 1.5% increase).

Reference Hint

Florida Building Construction Standards and Practices - Chapter on Cost Estimating and Project Management, or Construction Cost Estimating reference materials covering escalation calculations

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.