EstatePass
al-supplementAlabama State Supplementmedium

A contractor in Alabama completes a $45,000 residential addition project. The homeowner fails to pay the final $8,500 invoice. What is the maximum time limit to file a mechanics' lien under Alabama law?

Correct Answer

A) 120 days from completion

Under Alabama lien law, contractors have 120 days from completion of work to file a mechanics' lien.

Answer Options
A
120 days from completion
B
60 days from completion
C
90 days from completion
D
180 days from completion

Why This Is the Correct Answer

Under Alabama lien law, contractors have 120 days from completion of work to file a mechanics' lien.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.