EstatePass
Business & FinanceAccountingmedium32% of exam part

A contractor has the following for a specific project: Original contract $200,000, approved change orders $25,000, costs incurred to date $180,000, estimated costs to complete $30,000. What is the projected profit/loss for this project?

Correct Answer

B) $15,000 profit

Total contract value = $200,000 + $25,000 = $225,000. Total estimated costs = $180,000 + $30,000 = $210,000. Projected profit = $225,000 - $210,000 = $15,000 profit.

Answer Options
A
$25,000 profit
B
$15,000 profit
C
$45,000 profit
D
$15,000 loss

Why This Is the Correct Answer

To calculate projected profit/loss, you must first determine the total contract value by adding the original contract amount to approved change orders ($200,000 + $25,000 = $225,000). Then calculate total estimated project costs by adding costs incurred to date plus estimated costs to complete ($180,000 + $30,000 = $210,000). The projected profit is the difference between total contract value and total estimated costs ($225,000 - $210,000 = $15,000 profit).

Why the Other Options Are Wrong

Option C: $45,000 profit

This incorrectly shows a loss instead of profit, likely from subtracting the contract value from the costs rather than costs from contract value, or from failing to include approved change orders in the total contract value calculation.

Option D: $15,000 loss

This amount ($45,000) would result from incorrectly calculating either the total contract value or total costs, possibly by not including the estimated costs to complete ($30,000) in the total cost calculation.

Memory Technique

Remember 'RICE': Revenue (contract + changes) minus Incurred costs minus Estimated remaining costs = profit/loss

Reference Hint

Look up project cost control and profit/loss calculations in the Business and Finance Management chapter of your contractor reference manual

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.