A contractor has the following for a project: Contract amount $400,000, Costs incurred $240,000, Estimated costs to complete $120,000. What percentage of the project is complete using the cost-to-cost method?
Correct Answer
D) 67%
Percentage complete = Costs incurred ÷ Total estimated costs. Total estimated costs = $240,000 + $120,000 = $360,000. Percentage complete = $240,000 ÷ $360,000 = 66.7% or 67%.
Why This Is the Correct Answer
The cost-to-cost method calculates project completion percentage by dividing costs incurred by total estimated project costs. Total estimated costs equal costs incurred ($240,000) plus estimated costs to complete ($120,000), which equals $360,000. Dividing costs incurred ($240,000) by total estimated costs ($360,000) gives 66.7%, which rounds to 67%.
Why the Other Options Are Wrong
Option A: 60%
75% would result from an incorrect calculation, possibly confusing the denominator or using wrong cost figures in the cost-to-cost formula.
Option C: 75%
60% would result from incorrectly dividing costs incurred ($240,000) by the contract amount ($400,000), which is not the cost-to-cost method formula.
Memory Technique
Remember 'CTC' - Cost-To-Cost method uses Costs incurred divided by Total Costs (incurred plus remaining costs to complete).
Reference Hint
Look up 'Percentage of Completion Method' or 'Cost-to-Cost Method' in accounting or project management sections of your reference materials.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
A contractor's cash flow projection shows receipts of $85,000 and disbursements of $92,000 for next month. The current cash balance is $15,000. What action should the contractor take?
Next Question
When establishing professional relationships on a construction project, who is typically responsible for ensuring that structural modifications comply with building codes?
