EstatePass
Business & FinanceAccountingmedium32% of exam part

A contractor has the following for a project: Contract amount $400,000, Costs incurred $240,000, Estimated costs to complete $120,000. What percentage of the project is complete using the cost-to-cost method?

Correct Answer

D) 67%

Percentage complete = Costs incurred ÷ Total estimated costs. Total estimated costs = $240,000 + $120,000 = $360,000. Percentage complete = $240,000 ÷ $360,000 = 66.7% or 67%.

Answer Options
A
60%
B
80%
C
75%
D
67%

Why This Is the Correct Answer

The cost-to-cost method calculates project completion percentage by dividing costs incurred by total estimated project costs. Total estimated costs equal costs incurred ($240,000) plus estimated costs to complete ($120,000), which equals $360,000. Dividing costs incurred ($240,000) by total estimated costs ($360,000) gives 66.7%, which rounds to 67%.

Why the Other Options Are Wrong

Option A: 60%

75% would result from an incorrect calculation, possibly confusing the denominator or using wrong cost figures in the cost-to-cost formula.

Option C: 75%

60% would result from incorrectly dividing costs incurred ($240,000) by the contract amount ($400,000), which is not the cost-to-cost method formula.

Memory Technique

Remember 'CTC' - Cost-To-Cost method uses Costs incurred divided by Total Costs (incurred plus remaining costs to complete).

Reference Hint

Look up 'Percentage of Completion Method' or 'Cost-to-Cost Method' in accounting or project management sections of your reference materials.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.