EstatePass
al-supplementAlabama State Supplementmedium

A contractor files a mechanic's lien in Alabama for $45,000. What is the required bond amount to contest this lien?

Correct Answer

D) $67,500

Alabama requires a bond of 150% of the lien amount to contest. $45,000 × 1.5 = $67,500.

Answer Options
A
$45,000
B
$90,000
C
$56,250
D
$67,500

Why This Is the Correct Answer

Alabama requires a bond of 150% of the lien amount to contest. $45,000 × 1.5 = $67,500.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.