EstatePass
al-supplementAlabama State Supplementmedium

A contractor files a mechanic's lien in Alabama for $45,000 of unpaid work. If the lien is foreclosed and the property sells for $38,000 after legal fees of $3,200, how much can the contractor recover?

Correct Answer

C) $34,800

The contractor can recover the net proceeds after legal fees: $38,000 - $3,200 = $34,800, which is less than the lien amount.

Answer Options
A
$45,000
B
$38,000
C
$34,800
D
$41,800

Why This Is the Correct Answer

The contractor can recover the net proceeds after legal fees: $38,000 - $3,200 = $34,800, which is less than the lien amount.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.