EstatePass
NASCLAContractsmedium15% of exam part

A contractor discovers unforeseen rock excavation that will cost an additional $45,000. The change order includes 15% markup for overhead and profit. If the owner retains 10% on all work, what is the net payment to the contractor for this change order?

Correct Answer

A) $46,575

Cost with markup: $45,000 × 1.15 = $51,750. Net payment after 10% retainage: $51,750 × 0.90 = $46,575.

Answer Options
A
$46,575
B
$40,500
C
$51,750
D
$57,500

Why This Is the Correct Answer

Cost with markup: $45,000 × 1.15 = $51,750. Net payment after 10% retainage: $51,750 × 0.90 = $46,575.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.