EstatePass
Business & FinanceOperationsmedium10% of exam part

A contractor discovers that a key material supplier cannot deliver concrete on the scheduled date, potentially delaying the critical path by 3 days. What is the most appropriate immediate action?

Correct Answer

A) Find an alternative supplier or expedite delivery from another source

When facing a critical path delay due to material availability, the first action should be to expedite delivery through alternative suppliers or methods. This maintains the original schedule and avoids costly delays.

Answer Options
A
Find an alternative supplier or expedite delivery from another source
B
Switch to a different construction method
C
Accept the delay and adjust the overall schedule
D
Crash other activities to make up the time

Why This Is the Correct Answer

Option C is correct because when facing a critical path delay, the immediate priority is to maintain the original schedule through alternative sourcing. Finding another supplier or expediting delivery addresses the root cause of the problem without accepting delays or making costly changes to the project. This approach preserves the project timeline and budget while solving the immediate material availability issue. It's the most direct and cost-effective solution that maintains project momentum.

Why the Other Options Are Wrong

Option B: Switch to a different construction method

Option B is wrong because crashing other activities is expensive and should only be considered after exhausting material sourcing options. Crashing involves adding resources or working overtime, which increases costs significantly. It's premature to crash activities when the original problem (material availability) might be solvable through alternative suppliers.

Option C: Accept the delay and adjust the overall schedule

Option A is wrong because accepting delays should be a last resort, not the immediate action. Simply adjusting the schedule without first attempting to resolve the material issue ignores potential solutions and unnecessarily extends the project timeline, which can lead to increased costs, contract penalties, and cascading delays to other project activities.

Memory Technique

Think 'SOURCE first' - when materials are the problem, find alternative SOURCES before accepting delays or making expensive changes

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and schedule compression techniques

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.