A contractor discovers an active osprey nest on a cell tower that needs modification. Construction is scheduled to begin during nesting season. What is the most appropriate action?

Correct Answer

C) Delay construction until after nesting season

Ospreys are protected, and active nests cannot be disturbed during nesting season. Construction should be delayed until after nesting season or appropriate wildlife agency consultation and permits are obtained.

Answer Options
A
Apply for an emergency construction permit
B
Relocate the nest before construction begins
C
Delay construction until after nesting season
D
Work around the nest with reduced noise levels

Why This Is the Correct Answer

Ospreys are federally protected under the Migratory Bird Treaty Act, making it illegal to disturb active nests during nesting season without proper permits. The safest and most legally compliant approach is to delay construction until after the nesting season ends, typically in late summer or early fall. This avoids potential federal violations and costly project delays that could result from enforcement actions. Wildlife protection laws take precedence over construction schedules.

Why the Other Options Are Wrong

Option A: Apply for an emergency construction permit

Working around the nest, even with reduced noise levels, still constitutes disturbance of a protected species during nesting season. Any construction activity near an active nest is considered harassment under federal wildlife protection laws.

Option B: Relocate the nest before construction begins

Emergency construction permits do not override federal wildlife protection laws. Such permits are typically for immediate safety hazards, not routine construction projects, and would still require wildlife agency coordination.

Memory Technique

Think 'OSPREY = OBEY' - when you see protected wildlife, you must obey federal law and stop work until the coast is clear

Reference Hint

Florida Building Code Chapter 1, Administrative provisions regarding regulatory compliance, or environmental regulations section

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.