A contractor completes work on March 15th but the owner refuses final payment. Under Alabama mechanics' lien law, what is the deadline to file the lien?
Correct Answer
D) July 14th (120 days)
Alabama mechanics' lien law requires liens to be filed within 120 days of completion of work or last furnishing of materials.
Why This Is the Correct Answer
Alabama law requires mechanics' liens to be filed within 120 days of completion. Counting 120 days from March 15: March has 16 remaining days (15th to 31st), April = 30, May = 31, June = 30, July = 3 — totaling 120 days, placing the deadline on July 14th.
Why the Other Options Are Wrong
Option A: May 14th (60 days)
May 14th represents only 60 days from March 15th, which is the deadline used in some other states. Alabama's 120-day rule gives contractors twice that long, so May 14th would cause a contractor to file unnecessarily early or mistakenly think they missed the window.
Option B: September 13th (180 days)
September 13th is 182 days from March 15th, roughly 6 months. This exceeds Alabama's 120-day filing window; a lien filed on September 13th would be untimely and unenforceable.
Option C: June 13th (90 days)
June 13th corresponds to approximately 90 days from March 15th — the deadline used by several neighboring states. Alabama's statutory period is 120 days, so June 13th would be 30 days too early to be the 'maximum' deadline.
Memory Technique
March 15 + 4 months = July 15, minus 1 day = July 14. Use the 'add 4 months, subtract 1 day' shortcut for any Alabama lien deadline question. Four months because 120 days ≈ 4 months.
More Alabama Questions
An Alabama licensed contractor is required to complete continuing education. How many hours are required for license renewal?
According to Alabama building codes, what is the maximum allowable deflection for floor joists under live load?
Which continuing education topic is mandatory for Alabama contractor license renewal?
Under Alabama building codes, which edition of the International Building Code (IBC) is currently adopted?
Under Alabama law, what is the statute of limitations for filing a breach of contract claim against a contractor?
A homeowner hires you for a $25,000 kitchen renovation but refuses to pay the final $5,000. You properly file a mechanics' lien. The homeowner wants to sell the house. What happens to your lien?
Which continuing education topic is specifically mandated by Alabama for contractor license renewal?
A contractor discovers that their Alabama contractor license expired 45 days ago. What is the consequence under Title 34-8?
Your client wants to add a 500 sq ft addition to their home. You discover during construction that the existing electrical system doesn't meet current Alabama electrical code. What is your obligation?
A contractor is building a residential foundation in Alabama clay soil. The soil report indicates expansive clay with a plasticity index of 35. What is the minimum recommended foundation depth?