A contractor completes a $45,000 residential addition. The homeowner pays $40,000 but disputes the final $5,000. Under Alabama lien law, when does the lien claim period begin?

Correct Answer

C) When the work is completed

Under Alabama lien law, the lien claim period begins when the work is completed, regardless of payment disputes or partial payments.

Answer Options
A
When payment becomes due
B
When the dispute arises
C
When the work is completed
D
When the partial payment is made

Why This Is the Correct Answer

Under Alabama lien law, the lien claim period begins when the work is completed, regardless of payment disputes or partial payments.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.