EstatePass
AlabamaAL Supplementeasy100% of exam part

A contractor completes a 2,400 square foot home addition. The total project cost is $180,000. What is the required permit fee if Alabama charges $0.75 per square foot plus a base fee of $150?

Correct Answer

C) $1,950

Permit fee = (2,400 sq ft × $0.75) + $150 = $1,800 + $150 = $1,950.

Answer Options
A
$1,650
B
$2,100
C
$1,950
D
$1,800

Why This Is the Correct Answer

Option C ($1,950) is correct. Permit fee = (Square footage × Rate) + Base fee = (2,400 × $0.75) + $150 = $1,800 + $150 = $1,950. The fee is based on square footage, not project cost — the $180,000 project cost is a red-herring piece of information included to test whether candidates know which variable to use.

Why the Other Options Are Wrong

Option A: $1,650

$1,650 does not result from correctly applying the given formula. It may result from using an incorrect square footage figure or rate. If a student used 2,000 sq ft instead of 2,400: (2,000 × $0.75) + $150 = $1,650 — a common mistake if the square footage is misread.

Option B: $2,100

$2,100 might result from using $0.75 per sq ft without accounting for base fee, or from applying the rate to the wrong base. No standard calculation from the given figures produces $2,100.

Option D: $1,800

$1,800 is the square footage component alone (2,400 × $0.75 = $1,800) without adding the $150 base fee. This is the most likely error — completing the multiplication step but forgetting to add the fixed base fee.

Memory Technique

Permit fee = 'Rate × Size + Base.' Always identify: What is the rate applied to? (Square footage here, not cost.) Then add any fixed base fee on top. Think of it like a taxi ride: the meter rate × distance, plus a flat pickup fee.

Was this explanation helpful?

More Alabama Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.