EstatePass
nascla-commercial-gcFinancial Managementeasy

A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?

Correct Answer

A) $250,000

Total job cost = Direct labor ($85,000) + Direct materials ($120,000) + Overhead ($45,000) = $250,000

Answer Options
A
$250,000
B
$165,000
C
$205,000
D
$230,000

Why This Is the Correct Answer

Option B is correct because total job cost includes all three components of project costs: direct labor ($85,000), direct materials ($120,000), and overhead costs ($45,000). Adding these together: $85,000 + $120,000 + $45,000 = $250,000. This represents the complete cost accounting for a construction project, including all direct and indirect expenses necessary to complete the work.

Why the Other Options Are Wrong

Option B: $165,000

Option C ($165,000) is incorrect because it only includes direct labor ($85,000) and overhead costs ($45,000), totaling $110,000, or possibly direct materials ($120,000) and overhead ($45,000). Either way, it omits a major cost component and significantly underestimates the total project cost.

Option D: $230,000

Option D ($230,000) is incorrect because it appears to be missing $20,000 from the total calculation. This could result from a mathematical error or potentially omitting a portion of one of the cost categories, but doesn't represent the complete sum of all three cost components.

Memory Technique

Remember 'DLM-O': Direct Labor + Materials + Overhead = Total job cost. Think 'DLMO' like 'DEMO' - you need all components to demonstrate the complete project cost.

Was this explanation helpful?

More nascla-commercial-gc Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing