A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
Correct Answer
A) $250,000
Total job cost = Direct labor ($85,000) + Direct materials ($120,000) + Overhead ($45,000) = $250,000
Why This Is the Correct Answer
Option B is correct because total job cost includes all three components of project costs: direct labor ($85,000), direct materials ($120,000), and overhead costs ($45,000). Adding these together: $85,000 + $120,000 + $45,000 = $250,000. This represents the complete cost accounting for a construction project, including all direct and indirect expenses necessary to complete the work.
Why the Other Options Are Wrong
Option B: $165,000
Option C ($165,000) is incorrect because it only includes direct labor ($85,000) and overhead costs ($45,000), totaling $110,000, or possibly direct materials ($120,000) and overhead ($45,000). Either way, it omits a major cost component and significantly underestimates the total project cost.
Option D: $230,000
Option D ($230,000) is incorrect because it appears to be missing $20,000 from the total calculation. This could result from a mathematical error or potentially omitting a portion of one of the cost categories, but doesn't represent the complete sum of all three cost components.
Memory Technique
Remember 'DLM-O': Direct Labor + Materials + Overhead = Total job cost. Think 'DLMO' like 'DEMO' - you need all components to demonstrate the complete project cost.
More nascla-commercial-gc Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During project closeout, the owner requests training for their maintenance staff on new building systems. This was not included in the original contract scope. What should the general contractor do?
Next Question
A building requires 8 accessible parking spaces. How many of these must be van-accessible according to ADA requirements?