A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
Correct Answer
A) $70,000
Working capital = Current assets - Current liabilities = $350,000 - $280,000 = $70,000. This represents the company's short-term financial health.
Why This Is the Correct Answer
Working capital is calculated by subtracting current liabilities from current assets. This formula measures a company's short-term liquidity and ability to meet immediate obligations. With current assets of $350,000 and current liabilities of $280,000, the working capital equals $350,000 - $280,000 = $70,000. This positive working capital indicates the company has sufficient short-term assets to cover its short-term debts.
Why the Other Options Are Wrong
Option B: $630,000
$350,000 only represents the current assets amount without subtracting current liabilities. While current assets are part of the working capital calculation, the complete formula requires subtracting current liabilities to determine net working capital.
Option D: $350,000
$280,000 only represents the current liabilities amount without any calculation. This ignores the current assets entirely and doesn't follow the working capital formula. Simply stating one component of the equation is not the answer.
Memory Technique
Remember 'Working Capital = What you CAN use' - Current Assets minus Current liabilities gives you what's left to WORK with.
More nascla-commercial-gc Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A project requires 2,400 square feet of 6-inch concrete slab. Material costs are: concrete $120/cubic yard, rebar $0.85/lb, vapor barrier $0.12/sq ft. Rebar requirement is 2.5 lbs/sq ft. What is the total material cost?
Next Question
During project closeout, what is the typical sequence for punch list completion?