A concrete mix design specifies a water-cement ratio of 0.45. If 600 pounds of cement are used, how many gallons of water should be added?
Correct Answer
D) 32.4 gallons
Water needed = 600 lbs × 0.45 = 270 lbs. Since water weighs 8.34 lbs per gallon, 270 ÷ 8.34 = 32.4 gallons. The water-cement ratio is critical for concrete strength and workability.
Why This Is the Correct Answer
The water-cement ratio of 0.45 means 0.45 pounds of water per pound of cement. With 600 pounds of cement, we need 600 × 0.45 = 270 pounds of water. Converting to gallons requires dividing by water's weight of 8.34 pounds per gallon: 270 ÷ 8.34 = 32.4 gallons. This calculation properly accounts for the unit conversion from weight to volume.
Why the Other Options Are Wrong
Option A: 27 gallons
This answer (45 gallons) appears to come from dividing 270 pounds by 6 instead of 8.34, showing a fundamental error in water weight conversion.
Option C: 45 gallons
This answer (36 gallons) likely comes from using an incorrect water density (7.5 lbs/gallon) or rounding errors in the calculation process.
Memory Technique
Remember '8.34' as 'Ate Three Four' - the weight of water per gallon that you 'ate, then three, then four' to memorize this critical conversion factor.
Reference Hint
ACI 211 - Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete, or concrete technology sections in construction reference manuals
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
An electrician needs to perform maintenance on a 480V electrical panel. Which lockout/tagout procedure component is most critical?
Next Question
A worker is exposed to lead dust during renovation work. The 8-hour time-weighted average exposure exceeds 30 micrograms per cubic meter. What action is required?
