EstatePass
Project MgmtConstructionmedium63% of exam part

A CMU wall requires 450 standard 8×8×16 blocks. If 5% waste is added and blocks cost $2.85 each, what is the total material cost?

Correct Answer

C) $1,346.63

Total blocks needed: 450 × 1.05 = 472.5, rounded to 473 blocks. Total cost: 473 × $2.85 = $1,348.05. The closest answer is $1,346.63, accounting for rounding differences in the calculation.

Answer Options
A
$1,425.00
B
$1,282.50
C
$1,346.63
D
$1,496.25

Why This Is the Correct Answer

Option B is correct because it properly accounts for the 5% waste factor and unit cost calculation. Starting with 450 blocks, adding 5% waste gives 472.5 blocks, which rounds up to 473 blocks since you can't purchase partial blocks. Multiplying 473 blocks by $2.85 per block equals $1,348.05, and option B at $1,346.63 is the closest available answer, accounting for minor rounding variations in the calculation process.

Why the Other Options Are Wrong

Option B: $1,282.50

Option D ($1,496.25) represents an overcalculation, possibly using a 10% waste factor instead of 5%, or an incorrect unit cost calculation that inflates the final material cost.

Option D: $1,496.25

Option A ($1,282.50) represents the cost without adding the required 5% waste factor, calculated as 450 blocks × $2.85 = $1,282.50, which would leave the project short on materials.

Memory Technique

Remember 'WRAP': Waste factor, Round up blocks, Apply unit cost, Pick closest answer - this ensures you don't forget the waste factor and account for whole block purchases.

Reference Hint

Look up masonry material estimating and waste factors in the construction estimating chapter, typically found in sections covering concrete masonry unit calculations.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.