A California contractor wants to make a change to an existing home improvement contract that will increase the total contract price by $3,500. According to B&P Code 7159, what documentation is required?
Correct Answer
C) A written change order signed by both parties
B&P Code 7159(d) requires that any changes to a home improvement contract that alter the contract price or scope of work must be documented in a written change order signed by both the contractor and the buyer before the changed work begins.
Why This Is the Correct Answer
B&P Code 7159(d) requires any modification to a home improvement contract that alters the contract price or scope of work to be documented in a written change order signed by both the contractor and the buyer before the changed work begins. At $3,500, this change clearly exceeds any threshold and requires full written documentation.
Why the Other Options Are Wrong
Option A: Change orders are not permitted once a contract is signed
Change orders are absolutely permitted after a contract is signed β they are a standard and expected part of construction. The law governs how they must be documented, not whether they can occur. Prohibiting all changes after signing would make construction contracts unworkable.
Option B: Email confirmation from the homeowner
Email confirmation alone is not sufficient under B&P Code 7159. The statute requires a formal written change order signed by both parties. An email from the homeowner, while written, does not constitute a properly executed change order.
Option D: Verbal agreement with the homeowner is sufficient
A verbal agreement with the homeowner, no matter how clearly communicated or agreed upon, does not satisfy B&P Code 7159's written change order requirement. Verbal agreements for contract modifications are unenforceable and expose the contractor to disputes and license violations.
Memory Technique
The rule is simple: '$0 change to scope or price = written change order required.' There is no minimum threshold for change order documentation in home improvement contracts β any price or scope change needs a signed written change order.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass