A built-up roof (BUR) system is being installed on a 10,000 square foot warehouse. The specification calls for a 4-ply system with hot asphalt between plies. Approximately how many pounds of asphalt will be needed for the inter-ply mopping at 25 lbs per 100 square feet per ply?

Correct Answer

A) 7,500 lbs

A 4-ply system has 3 inter-ply moppings (between plies). Total asphalt = 10,000 sq ft × 3 moppings × 25 lbs per 100 sq ft = 10,000 × 3 × 0.25 = 7,500 lbs. The flood coat and base mopping are typically specified separately.

Answer Options
A
7,500 lbs
B
15,000 lbs
C
12,500 lbs
D
10,000 lbs

Why This Is the Correct Answer

A 4-ply system has 3 inter-ply moppings (between plies). Total asphalt = 10,000 sq ft × 3 moppings × 25 lbs per 100 sq ft = 10,000 × 3 × 0.25 = 7,500 lbs. The flood coat and base mopping are typically specified separately.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing