A building section drawing shows a detail reference bubble with '7/A-5' inside. What does this notation indicate?
Correct Answer
B) Detail 7 on sheet A-5
The notation '7/A-5' in a reference bubble indicates detail number 7 found on sheet A-5. This cross-referencing system helps users locate detailed drawings throughout the drawing set.
Why This Is the Correct Answer
The notation '7/A-5' follows the standard architectural drawing convention for detail reference bubbles. The number before the slash (7) indicates the detail number, while the designation after the slash (A-5) indicates the sheet where that detail can be found. This cross-referencing system is universally used in construction drawings to help contractors and workers quickly locate specific details throughout the drawing set. Detail reference bubbles are essential navigation tools that prevent confusion and ensure accurate construction.
Why the Other Options Are Wrong
Option C: Section 7 taken at grid line A-5
Section references use different notation and typically show cutting plane lines with arrows indicating viewing direction. Section bubbles would not reference grid lines in this format, and sections are usually numbered differently with their own reference system.
Option D: Room 7 in building phase A-5
Elevation callouts use different symbols and notation systems, typically showing height measurements or finish floor elevations. The format '7/A-5' is not used for elevation references, which would more commonly show actual elevation numbers or relative heights.
Memory Technique
Think 'Detail/Destination' - the detail number comes first, then the slash points you to the destination sheet where you'll find it.
Reference Hint
Look up 'Architectural Drawing Standards' or 'Detail Reference Systems' in construction drawing interpretation guides, typically found in blueprint reading chapters.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which welding process is most commonly used for structural steel connections in commercial construction?
Next Question
A site plan indicates a building setback of 25 feet from the front property line. If the building is 40 feet deep and the lot is 100 feet deep, what is the rear yard depth?